Apartment has not received the acceptance result and has not been handed over the house yet
Mon, 15 Jun 2020 13:14:00 | Print | Email Share:
Here, an investor brings a work or work item into operation without a written approval of the investor's acceptance result, it is a violation of the regulations on construction work quality control.
Mr. Bui Phuc (in Hanoi) bought an apartment of 34-floor Ecogreen project invested by Viet Hung Real Estate and Construction Co., Ltd. The building has a building inspection document issued by the State Department of Inspection of quality of construction works in July 2018.
However, the investor handed over to residents in February 2018, Mr. Phuc would like to ask, is it true to the regulations on the quality management of construction?
The Ministry of Construction answers this issue as follows:
The content of the question mentioned is not clear and full of information about the 34-storey Ecogreen project, we understand that it may be a project of Commercial Complex, Supermarket, Office and Housing for sale Eco - Green City, Construction site in Southwestern Kim Giang New Urban Area, Tan Trieu Commune, Thanh Tri District, Hanoi City is invested by Viet Hung Real Estate and Construction Co., Ltd.
This work is subject to the State Department of Construction Quality Inspection - Ministry of Construction checked the acceptance work in accordance with Article 32 of Decree No. 46/2015 / ND-CP dated May 12, 2015 of Government on quality management and maintenance of construction works.
The Department of State Quality Inspection of construction works held an inspection and approved in writing the investor's results of pre-acceptance test of construction items, at the following times: CT4 was approved in September 2017, CT3 and CT1 buildings were approved in April 2018, CT2 building and basement items were approved in July 2018.
According to Clause 4, Article 31 of Decree No. 46/2015 / ND-CP, conditions for putting works and work items into use are: Works and work items that are tested and accepted according to regulations; It must be approved by the competent agency in charge of the pre-acceptance test and written approval of the test results of the investor.
Where an investor brings a work or work item into operation without a written approval of the investor's acceptance result, it is a violation of the regulations on construction work quality control.
Because Mr. Phuc's question does not specify which apartment of the project the apartment belongs to, so you need to base on the above rule to determine.
By: Online Newspaper of the Government / Translator: HaiYen-Bizic
---------------------------------------------