What land documents are required for a construction permit?
Sat, 24 May 2025 15:00:00
Ms. Le Thi Anh Nguyet works at the Management Board of Export Processing and Industrial Zones. Her agency is receiving applications for construction permits for projects investing in the construction and business of industrial park infrastructure.

In which cases can road use fees be refunded?
Sat, 24 May 2025 15:00:00
Mr. Nguyen Van Hai has a car that has paid the full road use fee for the entire inspection cycle. However, he has transferred the car to someone else and there are 16 months left until the new inspection cycle. Mr. Hai asked, is he eligible to get the road use fee refunded?

When must the contractor selection plan be adjusted?
Thu, 22 May 2025 15:00:00
On December 20, 2023, Mr. Tran Sinh Trai's agency (Hanoi) approved the contractor selection plan for the audit package. The package price is more than 200 million VND, the source of capital is state budget, the form of designated bidding, the time for organizing contractor selection is Quarter IV/2023, Quarter I/2024; lump sum contract type, contract implementation period is 120 days.

Procedures for implementing BOT projects for upgrading and expanding
Thu, 22 May 2025 15:00:00
Some BOT projects in the transport sector in the province of Mr. Nguyen Pham Thanh Huy, which were implemented since the early 2000s, have become overloaded and need investment in expansion to meet transportation needs and socio-economic development.

How to determine tax rate in bid price?
Tue, 20 May 2025 15:00:00
(Chinhphu.vn) - The bid price of the bidder must include all taxes, fees, and charges (if any) applied according to the tax rates, fees, and charges at 28 days prior to the bid closing date.

In which cases is it necessary to prepare a bid package estimate?
Tue, 20 May 2025 15:00:00
Ms. Le Thi Quynh Lan (Bac Ninh) asked, when organizing the plan to select a contractor, does the investor have to approve the bid package estimate? In case the bid package estimate (not the procurement estimate) must be approved, which level approves it?

Does the wastewater treatment plant have to be tested?
Wed, 30 Apr 2025 15:13:00
Ms. Nguyen Thi Lan's unit (Bac Giang) is implementing a limestone mining project, which has been approved by the Provincial People's Committee for investment policy decision, environmental impact assessment report and environmental license according to the Law on Environmental Protection 2020.

Determining environmental procedures for group III projects
Wed, 30 Apr 2025 15:13:00
Group III infrastructure investment projects generate 10 m3/day of domestic wastewater, 5 m3/day of industrial wastewater, regular hazardous waste under 100 kg/month, and negligible emissions.

When Can a Public Service Unit Independently Select a Contractor?
Wed, 30 Apr 2025 15:13:00
Ms. Tran Kim Hang (from Hung Yen) is currently working at a Group 2 public service unit that is financially self-sufficient in recurrent expenditures. The unit’s financial resources include both State budget allocations for assigned tasks and revenue from its professional service activities.

Environmental Documentation Requirements for Aquaculture Projects
Wed, 30 Apr 2025 15:13:00
Mr. Hoang Van Tung’s company, based in Lam Dong, operates in the field of cage aquaculture. The company runs a sturgeon farming facility with 220 cages, supplying approximately 170 tons of fish to the market annually. The total investment is VND 25 billion, and the water surface area used is 44.81 hectares (as per the permit for operating within the safety corridor of a hydropower reservoir).