Recommendation on inadequacies in contractor selection of projects invested by parent company - Song Da Corporation: According to the current bidding regulations, enterprises with capital contribution of more than 30% of the parent company are not allowed participation in bidding packages of projects invested by the parent company. This will hinder the creation of jobs for the member units through...

1) The government is working out a minimum wage schedule that sets a target for the long run. However, the fluctuations in domestic and international economic conditions are extremely difficult to forecast, The minimum wage should be determined based on economic indicators and annual economic trends. It is not appropriate to set a medium-term goal. 2) The minimum wage increases...

The pilot of auction of domestic cigarettes for domestic sale of illegally imported cigarettes confiscated and the quality is not compliant with the regulations on the system of legal documents on cigarettes consumed domestically. Direction: "For smuggled cigarettes which are confiscated and still have quality, experimentally auction implementation for domestic sale or re-export; The pilot duration is one year, then...

At present, there are dozens of enterprises specializing in exporting construction materials to Laos. However, in 2016, there were problems of the Circular No. 130/2016 / TT-BTC dated 12 August, therefore Enterprises can not operate, the reason are as follows The Law No 106 / 2016OH13 issued on April 6, 2016, on the amendment of laws including the Law on...

In 2008, implementing the policy of Ha Tinh Province to deploy a production area for infrastructure construction and preparation for the mining of Thach Khe Iron Mine, Thach Ha District, Ha Tinh Province, which is the area of construction materials, and there are regional plans and land use plans from 2005 - 2010, 2010 - 2015, 2016 - 2020, 2020...

The method of determining the unit price of works using state capital and works using non-state capital has created an unworthy precedent; there are many reputable and capable contractors that do not want participating in bidding packages using state capital for many reasons, including price and payment issues. In case of participation, if wining the contract, then it also find...

Detailed remedial measures are needed to address specific sectoral and project-specific regulations (both outstanding and future projects). • To develop the Law on Construction, the Law on Bidding for the Guarantee Mechanism of the Owner. Accordingly, when the value of the remaining package is from 30 to 40% (depending on the form of payment for the bidding package), the investor...

This is a very important issue in prices of real estates. - At present, the determination of land prices in projects is assigned to the People's Committee of provinces through adjustment coefficient k of the common land price. For example, the latest in Hanoi is the decision No 188 dated January 14, 2016 and in Ho Chi Minh City is...

According to Article 171 of the Law on Housing, there must be detailed plan drawings approved by competent state agencies before being approved. Meanwhile, under Article 31 of Decree 44/2015 / NDCP, it is clearly stated that the licensing planning is only granted to investors who are capable of implementing the investment in construction of the project. In case of...

Comments on the amendment and supplementation of the Decision No. 35/2015 / QD-TTg dated August 20, 2015 amending and supplementing the Decision No. 02/2012 / QD-TTG dated January 13, 2012 of the Government’s Prime Minister on the promulgation of the list of essential goods and services that must register the contract according to the form and general trading - The...

In the newly promulgated Law on Real Estate Business, the Article 56 has stipulated that the owner must buy a future housing guarantee when it is sold to the client during the construction process, but guidelines and regulations details of this regulation are still unclear and too late: The law comes into effect from July 1, 2015, but by September...

Le Quoc Co., Ltd was surprised to receive the Notice No. 3629 / TB-HQK VI dated June 23 2017 of the department of customs of Haiphong Port Area I on Hung Vuong fruit, vegetable, food and general Port - "No vessels and transport vehicles are allowed to receive for exit, entry or transit" that be taken by the deputy head...

The case of Long An Textile Joint Stock Company originated from 4 credit contracts, including 3 contracts with the wrong amount of "false" was 68 billion that I was the direct implementation with Merchants Bank Techcombank (Techcombank). After that, the 2 nd tribunal has adjudicated the Long An Textile Joint Stock Company to pay all 4 credit contracts by 2...

Bac Ha Energy Joint Stock Company (hereinafter referred to as Bac Ha Company) is the investor of Nam Phang B hydroelectricity project with a installed capacity of 4.5 MW in Bac Ha District, Lao Cai Province. The total reservoir volume is 208,000 m3 and the useful volume is 71,000 m3. Bac Ha Company has implemented the procedures for approval of...

- To propose the Vietnam Social Security to have comments to the Government and other related ministries on amendment and supplement the legal documents related to bidding to suit the reality after 4 years of implementation.. - To propose the Vietnam Ssocial Security to have comment to the Ministry of Health onamendment and supplement the circular related to the issuance...