Ialy expansion project’s second turbine connected to national grid

Mon, 16 Dec 2024 11:14:00  |  Print  |  Email   Share:

On the evening of December 13, the second turbine of the Ialy Hydropower Plant expansion project was successfully connected to the national power grid, which was 18 days ahead of schedule.

The second turbine of Ialy Hydropower Plant expansion project. (Photo: EVN)
The second turbine of Ialy Hydropower Plant expansion project. (Photo: EVN)

The Ialy Hydropower Plant expansion project, with Vietnam Electricity Group (EVN) as the investor, is a national key project that began construction in mid-2021.

The expansion has a design capacity of 360 megawatts, consisting of two turbines.

 

When operational, the facility will increase power generation capacity for the national power grid, especially during peak hours. It will optimise water resource utilisation and increase average annual power generation by approximately 233 million kWh/year.

The project also contributes to reducing carbon emissions and decreasing the intensity and operating time of existing turbines, thereby extending equipment lifespan and saving maintenance and repair costs.

Previously, the first turbine of the Ialy Hydropower Plant expansion project was successfully connected to the national power grid on November 26.

By: NDO

Source: https://en.nhandan.vn/ialy-expansion-projects-second-turbine-connected-to-national-grid-post142243.html

---------------------------------------------

Back     Up to top   

Same category News :

Copyright © 2016 by the Chamber of Commerce and Industry of Vietnam - VCCI
Write "Chamber of Commerce and Industry of Vietnam"
or www.vcci.org.vn; www.vcci.com.vn; www.vcci.net.vn the release of information from this Website.
Designed and developed by Vietkent