Vietnam’s Ministry of Industry and Trade held the signing ceremony in Hanoi, attended by Standing Deputy Prime Minister Pham Gia Tuc, Minister of Industry and Trade Le Manh Hung, Ninh Binh Party Secretary Tran Huy Tuan, and representatives of the investor, state utility Electricity of Vietnam (EVN), and mining group TKV.
The BOT contract signing marks a transition from a prolonged period of preparation and negotiations to the implementation of subsequent investment procedures and project work.
It also lays the groundwork for the parties to finalize key agreements and add large-scale power generation capacity to the national grid, amid rising electricity demand in northern Vietnam.
The Nam Dinh I BOT thermal power project, spanning nearly 243 hectares in the former Nam Dinh province, now part of Ninh Binh province, received its investment registration certificate from Vietnam's Ministry of Planning and Investment on June 15, 2017.
The project was awarded to a consortium comprising South Korea's Taekwang Power and Saudi Arabia's Acwa Power through Nam Dinh First Power Co. Ltd., a Singapore-based project company.
With a designed capacity of 1,200 MW, comprising two 600 MW units, the project is among the key power generation developments included in the revised Power Development Plan VIII. The investor has committed to bringing the plant into commercial operation in 2030.
Commenting on the project, Nguyen Duc Cuong, director of the Electricity Authority of Vietnam under the Ministry of Industry and Trade, said the ministry had worked with relevant agencies to review project documents and reach agreement on principles for applying transitional regulations ahead of the signing.
The parties would not renegotiate terms they had previously agreed on and initialed in accordance with the law, he said. This approach provides a legal basis for the project to move forward.
Notably, the investor has formalized its commitment to reducing the project's emissions to levels comparable to those of LNG-fired power plants and bearing all associated additional costs.
According to the Electricity Authority of Vietnam, most key legal, technical and commercial conditions had essentially been met by the time the contract was signed, while the main agreements were ready for formal signing, paving the way for the implementation of related arrangements.
Speaking at the ceremony, Deputy Minister of Industry and Trade Truong Thanh Hoai stressed the project's importance to ensuring electricity supplies in northern Vietnam. Electricity demand is expected to continue rising sharply in 2027-2031, while adding new power generation capacity remains challenging. The north is both a major electricity consumption hub and home to numerous industrial facilities that support economic growth.
The deputy minister requested that the investors and the BOT company urgently finalize capital arrangements and fulfill all their obligations. They must ensure coordination with relevant Vietnamese stakeholders to complete power purchase agreements, land lease agreements, and fuel supply contracts, as well as fulfill all investment, construction, and environmental procedures in accordance with the law.
Furthermore, they are expected to proactively prepare the necessary human resources, equipment, and construction plans to commence work as soon as all regulatory requirements are met.
The Nam Dinh I Thermal Power Plant is designated as a baseload power source, capable of generating electricity steadily and being dispatched according to demand. The plant is expected to improve grid reliability and help balance electricity supplies as the share of renewable energy increases.
On fuel supply, Deputy Minister Hoai asked state-owned mining group TKV to work with the BOT company to review implementation of the coal supply contract, prepare supply sources and transportation and handling plans, and ensure sufficient volumes and quality for the plant's operation. State utility Vietnam Electricity (EVN) is required to sign the power purchase agreement soon and coordinate efforts to ensure timely grid connection and power evacuation.
At the same time, he requested that the Ninh Binh People’s Committee direct the completion of land lease procedures and the signing of land lease agreements; accelerate compensation, site clearance and resettlement efforts; and ensure the handover of the site according to the established schedule.
Representing the investor, Jin Sang Young, CEO of TKG Taekwang Group, pledged to mobilize resources to complete construction and bring the plant into commercial operation as soon as possible, while prioritizing efficiency, safety and environmental protection and contributing to the local community.
The Politburo's Resolution No. 70-NQ/TW identifies ensuring national energy security as a prerequisite for achieving double-digit economic growth.
Under the revised Power Development Plan VIII, total power generation capacity serving domestic demand is projected to reach 183,291-236,363 MW by 2030, with coal-fired power accounting for around 31,055 MW and continuing to play a baseload role in the energy transition.