Mr. Truong asked, so when preparing the bidding documents, can the investor build the content of the remaining chapters themselves?
On this issue, the Ministry of Finance has the following opinion:
According to the provisions of Clause 6, Article 4 of Circular No. 79/2025/TT-BTC dated August 4, 2025 of the Minister of Finance, for consulting service packages, Form No. 6A is used to prepare E-HSMT applying the form of open bidding, limited bidding in the form of one-stage two-envelope method.
Accordingly, in the case of your bidding package being a consulting package for construction supervision using public investment capital, it is implemented according to Form No. 6A issued with Circular No. 79/2025/TT-BTC (which includes the contents that have been digitized in the form of a webform or presented in the form of a file for the investor and the expert team to enter information to prepare E-HSMT).
Therefore, the contents of chapters 4, 5, 6, 7, 8 must be implemented according to the instructions in Form No. 6A above.