Fri, Aug 22, 2025, 10:59:00
Regarding this issue, the Ministry of Finance has the following comments:
According to Clause 1, Article 27 of Decree No. 24/2024/ND-CP, the evaluation of bidding documents must be based on the criteria for evaluating bidding documents and other requirements in the bidding documents, based on the submitted bidding documents, documents explaining and clarifying the bidding documents of the bidders to ensure the selection of bidders with sufficient capacity and experience, and feasible solutions to implement the bidding package.
Accordingly, the evaluation of E-HSDT (including the content of capacity and experience) complies with the above regulations and is the responsibility of the expert team and the bidding party.